Saturday 1 August 2020

Fire Signage Maintenance - Jan 2021 for BJH

It seems the fire escape signage is going to be checked and refreshed, including on balconies.

In Ben Jonson House we can expect to see activity on our balconies between the 4th to the 11th January 2021, so lots of time to plan (and pick off that faded fire-exit sign if you'd like a fresh new one (joke)).

Here is the BEO notice: 
___

Fire Signage Project


Continuing on from last year’s Fire Signage survey, Britannia Fire & Security Ltd, will start on the Barbican Estate from 10 August.

The work will include replacement and installation of fire signage in common areas and escape routes including balconies. Access will not be required to resident’s homes.

Please see the schedule of works below and contact the Major Works Team DCCS-MajorWorksTeam@cityoflondon.gov.uk if any queries.

 

 Block

Start Date

Completion Date

Cromwell Tower 13 days

10/08/2020

26/08/2020

Shakespeare Tower 12 days

27/08/2020

11/09/2020

Lauderdale Tower/Lambert Jones 11 days

14/09/2020

28/09/2020

Willoughby House 3 days

29/09/2020

01/10/2020

Speed House 5 days

02/10/2020

08/10/2020

Brandon Mews 1 day

09/10/2020

09/10/2020

Andrewes House 13 days

12/10/2020

29/10/2020

Gilbert House 3 days

29/10/2020

02/11/2020

The Postern 1 day

03/11/2020

03/11/2020

Mountjoy House 2 days

04/11/2020

05/11/2020

Thomas More House 10 days

06/11/2020

19/11/2020

Seddon House 2 days

20/11/2020

23/11/2020

Defoe House 10 days

24/11/2020

07/12/2020

John Trundle Court 5 days

08/12/2020

14/12/2020

Bunyan Court 3 days

15/12/2020

17/12/2020

Bryer Court 2 days

18/12/2020

21/12/2020

Ben Jonson House 6 days

04/01/2021

11/01/2021

Breton House 5 days

12/01/2021

18/01/2021

Frobisher Crescent 6 days

19/01/2021

26/01/2021

No comments :