Thursday 18 May 2017

Concrete Repairs - Schedule

Following on from the concrete survey and the concrete report, the BEO have produced a schedule of works to address the issues found.  The schedule covers the whole process from survey to repair, so most of the items on the schedule have already happened.  The outstanding one are in bold at the bottom.

Regarding costs, the schedule says that the exact costs will not be known until later this year, but the current estimated costs for Ben Jonson House are ~£140 per flat.
____

Most recent timeline of events is below:
  • December 2015 - Gateway 2 report approved the testing (and the "making safe" of any concrete whilst testing was being carried out but not any repairs)
  • January – June 2016 – concrete testing 
  • Summer/Early Autumn 2016 – collating, analysis and review of concrete testing results with recommendations provided by the consultants 
  • October/November 2016 – reports provided to the BEO by the consultants and also sent to RCC members and House Group Chairs
  • December 2016/January 2017 – preparation of Gateway 4 committee report on detailed options appraisal for the concrete testing 
  • February 2017 – Gateway 4 report presented to committee – this was approved Feb 2017 
  • February – June 2017 - Procurement as per City's Procurement Code - Consultants estimate is £28, 473 inclusive of fees & staff costs for Ben Jonson House, but this is an estimate and final figures will be confirmed once the tender process has been completed 
  • March 2017 – Stage 1 pre-tender Statutory Consultation with leaseholders - This went out in April 2017
  • July/August 2017 – Stage 2 Statutory Consultation with leaseholders (following review of tenders) - This is when we will be able to give residents exact costs involved. 
  • August 2017 – Gateway 5 report with delegated Chief Officer approval for commencement of works - This is now planned for September 2017 
  • August/September 2017 – commencement of works - This is now planned for October 2017