BMH: Developer Newsletter Jul 28

Here is the first newsletter for the BMH redevelopment project.  Sorry about the format.  I've asked the project communications people to use PDF in future ... and indeed Freddie of Cascade did send a PDF version which you can see here.
____

Weekly Construction Update - Bernard Morgan House

Welcome to the first Bernard Morgan House Weekly Construction Update. We will be sending these emails weekly throughout the demoltion and construction process.

Greater London Demolition (GLD) are now onsite conducting preparatory works, you will find an update of works due to take place during the next week below.

Residents can register to receive these emails by emailing: construction@cascadepr.co.uk.

Saturday 29th July
No works (GLD staff will be onsite carrying out admin in the site office).

Sunday 30th July
No works.

Monday 31st July to Friday 4th August
Preparatory works in the basement including preparation of pile holes.

Noise, dust and vibration monitoring takes place throughout the week to ensure that any disturbance for neighbours is reduced as much as possible.
Working Hours
The anticipated working hours are:

Monday to Friday 08.00 to 18.00
Saturday 09.00 to 14.00
No Sunday work

Anticipated Quiet times are
Monday to Friday 10.00-12.00
Monday to Friday 14.00-16.00

We will notify you of any changes to these working hours. Please note contractors may be onsite outside of these hours.

Contact Details

For urgent issues please contact Gary Telford, Site Manager: 07976 150854

For all other matters please contact Cascade Communications:
E: construction@cascadepr.co.uk
Freephone: 08081 686 677

Please do not hesitate to contact us.

A Construction Liaison Meeting was held on 17 July and attended by 23 members of the local community. A number of actions have taken place in response to issues raised at this meeting, including:
The onsite generator has been moved following concerns about noise.
Printing of a new sign clarifying that construction vehicles should not turn right onto Brackley Street.
Additional noticeboards are being arranged for the site hoardings. 

No comments :