Trial Holes for no.20 Ropemaker Street Development

Reach Active are undertaking trial hole excavation works on the footway and carriageway on Moor Lane and Silk Street from 3 December, to identify existing utility services. Work will continue on Ropemaker Street, Finsbury Pavement, South Place & Eldon Street.

The works started on 19 September on Moor Lane, with the intention of being completed Friday 21 with all works clear by close of play Monday 24.

Moorfields will start Monday 24 / Tuesday 25 September with the works taking 6 days. Site hours are 07:30 to 16:00 with noisy works between 08:00 to 10:00 and 12:00 to 14:00.

Pedestrian and vehicle access will be maintained, Please click here for details and see here for a map.