What the EIR response reveals
... for a pictorial historical context see the Fix The Drains album with images dating back to 2012!
November 2026
The City of London has provided six substantial documents in response to my Environmental Information Regulations (EIR) request concerning the proposed Barbican Podium Phase II works.
I've been reviewing these documents to understand why the City is proposing extensive resurfacing and waterproofing works, rather than first restoring the drainage system to full working order and then assessing what further repairs are necessary.
The documents contain some important findings.
Drainage problems were identified in 2018
The December 2018 Atkins Phase II Feasibility Study records a preliminary inspection by Lanes Group.
The drainage system inspected was in poor condition, with extensive scaling and obstructions. In one location, the available opening through which water could flow had been reduced to approximately 15 mm.
Atkins recommended that the condition of the drainage system be established through a full survey before remedial design proceeded.
This is significant. The engineers recognised that an understanding of the drainage system was essential to designing an effective solution.
By 2022, 106 of 109 phase II downpipes were obstructed
The November 2022 Phase II Design and Access Statement reports that Flowfree had inspected the downpipes serving the Phase II podium area.
Of the 109 downpipes identified, 106 were partially or completely blocked.
The statement explains that these pipes would need to be unblocked, repaired or replaced for the drainage system to function correctly.
It also refers to a separate Flowfree Drainage Survey Report containing details of the condition of individual pipes and the remedies required.
That report was not among the six documents supplied in response to my recent EIR request.
Phase I left drainage problems unresolved
The problems are not confined to the proposed Phase II area.
A June 2023 communication from Atkins, discussing lessons learned from Phase I at Beech Gardens, explicitly acknowledges that the under-podium drainage system was not included in those works.
It states that the exclusion meant some areas had not drained freely.
The December 2020 Phase II design-team presentation had already identified drainage repair and replacement as a lesson from Phase I.
For residents who continue to encounter substantial puddles on the refurbished highwalks, this is particularly relevant.
What about the waterproofing?
The documents also identify problems with the existing waterproofing, expansion joints and surface gradients.
These problems deserve attention. It would be wrong to conclude that clearing the drains must eliminate every instance of water penetration.
However, poor drainage, standing water and waterproofing defects are interconnected. Understanding those relationships matters when deciding what to repair and in what order.
The central question is whether the City has adequately established the extent to which restoring effective drainage could reduce the need for widespread intervention elsewhere.
What we still need to understand
Three important pieces of information remain outstanding:
The original project brief supplied to Atkins, including subsequent revisions.
The complete Flowfree Drainage Survey Report, including its recommendations.
The recorded decisions concerning what drainage repairs were authorised, completed or deferred following that survey.
I have made a further, narrowly focused EIR request for these records. The City acknowledged it on 23 November 2026.
We also need to understand how the proposed works fit into the drainage requirements of the wider Barbican Estate, rather than treating each refurbishment phase in isolation.
The case for getting drainage right first
I am not arguing that the Barbican podium requires no refurbishment. Nor am I arguing against waterproofing repairs where they are necessary.
My concern is that the drainage system is fundamental to the long-term performance of the podium, whether or not the surface is replaced.
A new surface and waterproofing system cannot compensate for neglected or ineffective drainage indefinitely.
Before proceeding with such extensive works, residents should be able to see a clear explanation of:
The condition and capacity of the drainage system, including its downstream connections.
What repairs are necessary to restore effective drainage.
How the system will subsequently be inspected and maintained.
Why the proposed extent of waterproofing and resurfacing remains necessary once drainage defects are addressed.
These are reasonable questions about a major programme of works on a listed estate.
The documents disclosed so far have helped establish what the City and its consultants knew about the drainage problems. They have not yet provided a complete explanation of how that knowledge informed the eventual scope of Phase II.
I'll publish further findings as the remaining information becomes available.
Sources: City of London EIR response, 20 November 2026; Atkins Phase II Feasibility Study, December 2018; Phase II Design and Access Statement, November 2022; Phase II design-team presentation, December 2020; Atkins Phase I to Phase II Lessons Learned, June 2023.
