Thursday, 22 October 2026

Barbican Library Refurbishment

 

The plan for the library ...

___


In my last email, I let you know that the refurbishment works at Barbican Library were due to start at the end of October. I can now confirm that the actual start date for these works will be Monday 2nd November 2026. This is to avoid the half-term holidays. The impact on the service will be as follows:

Children's Services

  • From Monday 2nd to Saturday 7th November, there will be no children's stock available for loan at Barbican Library.

  • Regular children's activities, such as Rhyme Time and Story Time, will still be taking place as usual, in an alternative location. Additional information about this will be sent to the email addresses registered on library accounts of children who are aged under 5 and through our Children's Newsletter service.

  • From Monday 9th November, for the duration of the works to the children's library, there will be a limited collection of children's books available for loan from the Bostock Community Meeting Room at the front of the library.


Music Services

  • From Monday 2nd to Saturday 7th November, there will be no music stock available from Barbican Library.

  • From Monday 9th November, there will be a limited collection of music-related books (no scores or CDs) available in the main library. CDs are still available at Shoe Lane Library and Artizan Street Library and Community Centre. You can reserve these items for free to be collected at Barbican Library.

  • At least one piano will be relocated to the main library, with booking and headphones available from the main library desk.


The Children's and Music libraries are expected to reopen at the beginning of January 2027.

I would like to remind you that we have now extended the number of items you can borrow as per below:

Item Current Temporary Extension
Books 12 20
CDs 12 16

Also, any items from the Barbican Children's and Music libraries will have their due dates automatically extended to 15th January 2027.

If you have an item with this date that is reserved by another user, we would be grateful if you could return it earlier for the person who is waiting for it. You will receive a Recall email if this is the case.

Thank you so much to all those who have filled out the survey to give us more details on the potential impact of the refurbishment works. Here is a summary of the main concerns and our response:

Concern Response
More limited physical stock collections During the refurbishment, unfortunately we will have to restrict the amount of stock available from different areas of the library at different times. We will do our best to provide a well curated selection of our most popular stock for each area affected. A full range of stock is available at Shoe Lane Library and Artizan Street Library and Community Centre, and you will be able to reserve items from these libraries for collection at Barbican Library for free. The extensive closed store of unique, significant and out of print books (adult only) held at Barbican Library will still be available for reservation for collection too.
Limited study/work space We are currently working with the Barbican Centre team to identify areas in the rest of the Centre where more tables and chairs can be provided for the duration of the refurbishment. There is also study/work space available at Shoe Lane and Guildhall libraries.
Events and groups We will relocate all our events and groups to other spaces in the Barbican Centre. Please look out for email updates regarding this if your regular event/group has an email list or see posters in the library.
Missing social connection/quiet space for mental wellbeing We appreciate that for many people, the library is an important part of their routine and a way to stay connected to others or take a quiet break. We will do our best to ensure there is still comfortable seating for those who need it, groups will still take place, and our staff will still be there to welcome people and assist.
Limited access to newspapers and magazines Newspapers and the most popular magazines will still be available throughout the project. A much larger range of magazines is available through our digital service.
Limited access to library computers During the second phase of works from January, when the main library will be refurbished, unfortunately there will be limited access to computers in the library, with only 3 available in the Music Library. Shoe Lane and Guildhall libraries do have sufficient numbers of computers available for public use.

And finally, thank you to all those who came to the information sessions or who sent me their queries and their lovely comments about the library and the team via email. We know how important Barbican Library is to all of its users and how cherished it is, and we really appreciate your support and patience during this time of disruption to the service.
Best wishes,

Rachel
Rachel Levy
Head of Barbican & Community Libraries - City of London Corporation

Thursday, 1 October 2026

Repairs Call Centre - It's the only way

The BEO is introducing a new dedicated call centre.  They prefer that we use the Barbican Estate app to raise new issues, but there is a phone number too: +44 207 029 3909.

The flyer includes the following note:

One way in, for everything. If something's broken, leaking, or not working, this is where it needs to be reported, whatever the issue and however it ends up being fixed. To make sure everything is properly logged, informal reporting routes are closing. Mentioning something to a porter, concierge, or contractor on site is no longer enough for it to be actioned, it needs to come through the App or the phone line so it gets a reference number. Out of hours emergency arrangements through your Concierge are not changing.
Here is the flyer:

Click to read the flyer

Saturday, 26 September 2026

Too hot, too cold?

 From the BEO:
___

Announcement title:Overheating and planning update

Dear Residents,

I hope everyone is well.

We recognise that the recently published revision of the National Planning Policy Framework following a campaign by the Duke of Westminster to modernise historic buildings. Policy CC3 (at page 30) now requires that "Substantial weight should be given to the benefits of improving the resilience of existing buildings and public spaces to anticipated climate change impacts.", which relaxes planning guidance when adapting listed buildings for climate change an important development for residents.

We also understand that long-term planning is critical, particularly when considering how our buildings can respond to increasingly frequent periods of hot weather. However, we also need to make sure that we can identify and deliver practical measures that can support residents in the shorter term. We are already working on this.

Our heating and overheating study by AMBUE is due to conclude later this year and will help us better understand the risks and identify appropriate measures for our diverse buildings. Alongside this work, we are already developing options and proposals for next summer, so that we can consider timely, project-based interventions to support residents during periods of hot weather.

Following the recent planning announcement, we have also specifically asked our consultants to consider the new guidance and its implications as part of their study. We want to ensure that it is properly reflected in their assessment recommendations, including any opportunities it may provide for future interventions.

This means we are taking a two-track approach:

  • Long term: using the study and wider building planning work to establish a robust approach to overheating and climate resilience.
  • Short term: developing practical measures and proposals that could be implemented ahead of, or during, next summer where appropriate.

We appreciate that residents need both a clear long-term plan and confidence that action is being taken now. We are therefore not waiting for the longer-term strategy to be completed before considering what can be done in the immediate future.

Once the study is complete and we have considered the consultants' findings alongside the updated planning guidance, we will be able to provide a clearer picture of the measures being considered and the next steps for residents.

I am conscious that I am writing about overheating just as it getting colder and the heating is about to come on! So, please be assured that that work is also being done to address this.

Thursday, 14 May 2026

Phase II: Drainage Defects Confirmed, But No Estate-Wide Strategy

 Further clarification has now been provided by Atkins and the City regarding the proposed Podium Phase II works.

Atkins have confirmed that CCTV drainage surveys were undertaken for podium downpipes within the Phase II area. According to Atkins, these surveys identified blockages and pipe defects requiring unblocking, repair and replacement as part of the proposed works.

Importantly, Atkins have also acknowledged that equivalent drainage remediation work was not undertaken as part of the earlier Phase I project.

This is significant because it now appears that substantial drainage defects have been identified within the podium drainage infrastructure itself, rather than the problem being solely one of failed waterproofing membranes or surface deterioration.

At the same time, Atkins continue to make clear that they were not asked to consider the podium drainage system from an estate-wide system level perspective. The City’s earlier FOI response also confirmed that:

  • no estate-wide hydraulic modelling of the podium drainage system has been undertaken,
  • no comprehensive estate-wide drainage strategy exists, and
  • no drainage maintenance records are held for recent years.

In light of this, an obvious question arises: would funds be better directed toward comprehensive drainage investigation and remediation across the estate as a whole, incorporating the lessons from Phase I, before proceeding with another major programme of demolition, strip-back and resurfacing works?

Another important point is the scope of the surveys themselves. While CCTV investigation of downpipes may identify local blockages and defects, it remains unclear whether this amounts to a comprehensive assessment of the wider podium drainage system and its long-term performance.

The project therefore still appears to be a localised intervention rather than part of a coordinated estate-wide drainage strategy.

Given the scale, cost and disruption associated with the proposed works, these seem entirely reasonable questions to ask before irreversible enabling works proceed.

Friday, 8 May 2026

Phase II: Atkins Confirm No Estate-Wide Drainage Review

 

Following further correspondence with the City and Atkins regarding the Barbican Podium Phase II works, an important clarification has now been provided in writing.

Atkins have confirmed that they were not asked to consider the podium drainage system from an estate-wide system level perspective, but rather to focus on the specific water ingress issues affecting the Phase II area.

This appears to confirm that the current project should be understood as a localised surface intervention rather than part of a coordinated estate-wide drainage strategy.

That distinction matters because the City’s recent FOI response also confirmed that:

  • no estate-wide hydraulic modelling of the podium drainage system has been undertaken,

  • no comprehensive estate-wide drainage strategy exists, and

  • no drainage maintenance records are held for recent years.

I have now asked for further clarification regarding what specific assessment of the drainage network itself has been undertaken even within the Phase II footprint.

For example, while trial holes and waterproofing investigations may help identify how water is entering the structure, they do not in themselves explain how the condition or performance of the drainage runs has been assessed, nor how confidence has been established that the proposed interventions will provide an effective long-term drainage solution.

Given the scale, cost and disruption associated with the proposed demolition and strip-back works, it seems reasonable that these technical questions should be satisfactorily resolved before irreversible enabling works proceed.

Tuesday, 5 May 2026

Podium Phase II: Progressing Without a Drainage Strategy?


The City has recently invited residents to a webinar on the Phase 2 podium works (details below).

By way of context, the response to a recent Freedom of Information request confirmed that:

  • no estate-wide drainage strategy or modelling has been undertaken, and
  • no drainage maintenance records are held for recent years.

Despite this, the City is continuing to progress the Phase 2 works, which are being presented as addressing long-standing drainage issues on the podium.

This is particularly notable given that similar drainage issues, including ponding, blocked drains and surface deterioration, are already visible on the western highwalk following the Phase 1 works.

This raises an obvious question: on what basis is it expected that these works will resolve drainage problems across the estate?

The webinar may be a useful opportunity to ask that question directly.


---

Dear Residents,

Following my update on 9 March 2026, I’m writing to invite you to an online webinar to meet the contractor and hear about the enabling works planned for this summer.

While we continue to discharge the pre-commencement planning conditions required for the main works, we are pleased to confirm that Maylim have been appointed as the contractor to commence early enabling works due to start this summer, including the removal of the Yellow Link Building.

Date: Monday 18 May 2026 Time: 18.30 - 19.30

Register: Please click this link to register or contact the project team via info@barbicanprojects.co.uk

In the webinar, Maylim will introduce the team and outline the proposed programme for the enabling works, including phasing, access arrangements, working hours, noise and other key considerations.

This will be followed by a Q&A session so you can ask questions and understand how the works may affect you.

We hope you are able to attend, but don’t worry if you can’t make it. The webinar will be recorded, and the presentation and recording be available on www.barbicanprojects.co.uk afterwards.

If you have any queries on the webinar, please contact the project team via info@barbicanprojects.co.uk or 0800 772 0475.

Kind regards, Dan Sanders, Director of Property and Estate Management - Barbican

Wednesday, 15 April 2026

Podium Phase 2 works: FOI request for drainage strategy

I submitted a Freedom of Information request on 9 March asking what analysis and planning had been undertaken over the years in relation to estate-wide drainage across the Barbican podium.

I received the response today. In short, the answer is: very little.

The City confirms that there is no estate-wide drainage strategy, no system-wide modelling, and no meaningful record of drainage maintenance.

The response is, in my view, quite revealing.

Below is a short summary of the key points arising.

--- 

Summary

The proposed Phase 2 podium works are being presented as a solution to long-standing drainage issues on the Barbican highwalks. However, information disclosed by the City of London under the Freedom of Information Act, together with earlier project documentation, raises serious questions about whether the underlying drainage problems are being addressed in a systematic and effective way.


Key Findings

1. No estate-wide drainage strategy or modelling
The City has confirmed that:

  • no estate-wide hydraulic modelling of the podium drainage system has been undertaken
  • no comprehensive estate-wide drainage strategy exists

Drainage is therefore not being managed as a coherent system, despite persistent issues across the estate.


2. No maintenance records for drainage infrastructure
The City has stated that:

  • no records are held for drainage maintenance, blockages, or clearance over the past five years

This makes it difficult to assess:

  • whether drainage problems are due to design or maintenance
  • whether proposed works will lead to measurable improvement

3. Phase 1 explicitly excluded drainage
A post-project technical review of earlier works states:

“This was a waterproofing project only… it would have been desirable to include podium drainage as well.”

Despite this acknowledged limitation, similar issues (ponding, blocked drains, surface deterioration) are already visible in the refurbished western highwalk.


4. Investigations are local, not system-wide
Recent technical work has focused on:

  • local leak investigations (e.g. Beech Gardens)
  • thermographic and radar surveys
  • structural movement monitoring

These are targeted diagnostics, not a comprehensive assessment of the drainage network across the estate.


5. Works are being delivered on a phased, project-by-project basis
The City confirms that podium works have been developed:

  • on a phased basis
  • informed by local condition and individual project approvals

There is no evidence of a coordinated, estate-wide approach to drainage infrastructure.


Implications

  • The root cause of drainage issues appears to be systemic rather than localised
  • Addressing drainage only within the Phase 2 footprint risks repeating the shortcomings of Phase 1
  • Without modelling, strategy, or maintenance data, it is unclear how improved drainage performance can be assured

Key Question

What estate-wide analysis has been undertaken to demonstrate that Phase 2 will resolve drainage issues at a system level, rather than simply within the project boundary?


Conclusion

There is a clear risk that Phase 2 prioritises surface renewal and capital works over addressing the underlying drainage system across the Barbican Estate. A more effective approach would be:

  • an estate-wide drainage assessment
  • a coordinated maintenance and repair programme
  • targeted surface works where required

Until such a strategy is in place, confidence in the long-term effectiveness of the proposed works is necessarily limited.

Tuesday, 10 March 2026

BEO enthusiasm for the Podium - Phase 2 works

The Barbican Estate Office is presenting Phase 2 as a major step forward for the podium. I am not persuaded. The real problem on the highwalks is drainage: drains that do not work properly and are not adequately maintained. Yet the proposed works are being promoted as though they will greatly improve conditions on the highwalks. That claim deserves scepticism.

We were told similar things around Phase 1, yet the western highwalk already shows puddles, blocked drains, staining and broken tiles. In practice, the result has been years of disruption followed by an area that looks little better and still suffers from the same underlying defects.

A more sensible approach would be an estate-wide programme of drain repair and maintenance, with local surface repairs where necessary, rather than another costly and disruptive capital project that risks treating the symptoms while leaving the cause in place.

From the BEO:
---

Barbican Podium - Phase 2

Dear Residents,

We are very pleased to confirm the Barbican Podium Phase 2 Project has now received approval for funding at the latest Court of Common Council meeitng. This important milestone means the project can now move into the next stage, where a contractor will be formally appointed to carry out the works.

Over the course of this year, we will focus on discharging the necessary pre-planning conditions required before construction can begin. One of the key early activities will be the removal of the Yellow Link Building, currently planned for this summer. In parallel, the project team will work to resolve the remaining contractual and technical matters, with the aim of achieving a Spring 2027 start on site.

As the programme moves into delivery, responsibility for the project will transition to a combined leadership between the Barbican Estate Office (Dan Sanders) and the Barbican Centre (Philippa Simpson), reflecting the significant impact the works will have across both the residential estate and the wider Barbican Renewal programme. This joint approach will help ensure that the needs of residents, the cultural centre, and the estate are considered throughout the project, and that all activity and design is fully coordinated.

This is a very exciting moment for the Barbican. The podium refurbishment represents a once-in-a-generation investment in the long-term future of the estate, helping to protect and enhance one of London's most iconic environments. We are committed to working openly and collaboratively with resident groups across the estate, ensuring clear communication and engagement as the project develops and construction approaches.

A core element of the works is the comprehensive upgrade of the podium drainage system. Addressing long-standing issues with water pooling across the podium is a major priority of the project. The scheme will also incorporate the drainage improvements originally intended as part of Phase 1 podium works but not delivered at that time, ensuring a more robust and resilient drainage network for the future.

Beyond resolving these technical issues, the project will deliver a range of wider benefits for residents and visitors. These include:

Improved drainage and waterproofing, protecting the buildings and facilities located beneath the podium structure and ending the water pooling following rainfall.

Enhanced landscaping and planting, supporting biodiversity and contributing to a greener, more climate-resilient estate.

Long-term protection of the Barbican's heritage, through sensitive refurbishment that respects the estate's Grade II listed status.

Better accessibility and legibility of the podium, making routes and spaces clearer and easier to navigate.

Integration with the wider Barbican Renewal programme, helping to secure the future of the Barbican as a world-leading cultural and residential destination for the next 50 years.

Taken together, these improvements will help ensure that the Barbican podium remains a welcoming, resilient, and vibrant place for residents, visitors, and nature, while safeguarding the estate's unique architectural character for generations to come.

We look forward to continuing to work with residents and stakeholders as the project progresses.

Sunday, 1 March 2026

90 Week Highwalk Resurfacing Project - More plans

 The City recently published two documents regarding the proposed 90 week project to strip back the eastern highwalk and relay it.  This is "phase 2" of the resurfacing work.  You can see the rather disappointing results of phase 1 as you walk towards the Barbican tube station, noting the blocked drains, cracked tiles and blocked direct route to the bridge (while they try to fix up something they missed in phase 1, no doubt).

The two documents are:

The wider issue of fixing the drains across the estate gets scant mention.  Rather, the focus is on the superficial works which, if you see the images in the document, will make the highwalk look lovely.  I recall similar documents for phase 1, and look at what we got.

To be fair I will note that the City does claim that they will apply a waterproof membrane beneath the new surfaces.  The problem is that a waterproof membrane without working drainage give you ponds, just as we see with the phase 1 work.

Anyway, I have written a letter to our councilors:

Dear [Councillors],

I note that the City is proceeding with Phase 2 of the podium works.

My concern is not that drainage works are absent, they are referenced in the documentation, but that they are:
1. Embedded within a much larger strip-back and landscaping project, and
2. Limited to the specific Phase 2 footprint rather than forming part of a coherent, estate-wide drainage strategy.

Drainage performance appears to be the fundamental issue affecting the highwalks (and indeed the structure of the Barbican!). Persistent ponding, blocked gullies and tile deterioration, including on the recently relaid western end, suggest systemic drainage shortcomings rather than isolated surface failures.

Blending drainage remediation into a predominantly surface-led scheme risks obscuring whether the underlying infrastructure is genuinely being resolved.

Before committing to 99 weeks of disruption, it would seem logical to:
- Publish a clear estate-wide drainage assessment,
- Confirm whether the wider podium drainage network has been surveyed in full,
- Explain why drainage is not being addressed comprehensively across the estate before further surface strip-back works proceed.

Without that clarity, this risks becoming a repeating cycle of surface renewal without structural resolution.

I would be grateful if you could seek a clear explanation from officers on how Phase 2 fits within a broader infrastructure strategy for the Barbican podium, in particular with respect to drainage.

Thursday, 22 January 2026

Lease Length and the 80-Year Threshold

From the BEO:


---------- Forwarded message ---------

Dear Leaseholders,
 

I hope you are well and that 2026 has begun positively.

I am writing to Barbican leaseholders to draw attention to an important matter concerning lease length and statutory lease extensions. This information will be most relevant to leaseholders who have not yet extended their leases, though it may not apply in all cases.

Many residential leases at the Barbican expire on or around 1 July 2106, with some variation between blocks. For leases that have not been extended, this means the remaining term will fall below 80 years from early July this year.

Under current leasehold legislation, once a lease has fewer than 80 years remaining, any statutory lease extension is subject to an additional element of premium known as "marriage value" (see the Leasehold Advisory Service definition Marriage value - The Leasehold Advisory Service). The inclusion of marriage value can significantly increase the cost of a lease extension and will usually require a professional valuation.

You may be aware that the Leasehold and Freehold Reform Act 2024 includes provisions to abolish marriage value. However, these provisions have not yet come into force, and there is currently no confirmed timetable for their implementation. Until the law changes, marriage value remains payable where a lease has fallen below the 80-year threshold.

While the City of London Corporation is unable to advise individual leaseholders, we wish to ensure that residents are fully informed. Leaseholders who have not yet extended their leases may therefore wish to consider beginning the statutory lease extension process before July this year. Serving the required statutory notice before a lease drops below 80 years would mean that marriage value does not apply under the current legal framework.

If you would like general information about the lease extension process, including the procedural steps involved, please contact: 

dccs-beo-servicecharges@cityoflondon.gov.uk

We recognise that the current uncertainty surrounding future legislative reform is unhelpful, and we will continue to monitor developments and keep leaseholders informed.

Our aim is always to support Barbican leaseholders by providing timely and transparent information, enabling leaseholders to make informed decisions.

Wednesday, 1 October 2025

1 Silk St. Planning Application - Huge Building



The planning application for the new building at 1 silk street is now live. Here is a letter from the Silk Street Campaign Team:

Dear Neighbours,

Many of you may now have received formal planning application letters from the City. Please find attached the latest Silk Street Campaign update, with details of a briefing meeting for residents to be held on 22 October.

Thank you for your support.

Silk Street Campaign Team
silkstreetcampaign@gmail.com

Here is the update which includes images showing just how big the proposed building is:

Another whopper - click to open the update


Monday, 25 August 2025

Bulky Waste Collections - the rules

The BEO asks that we dispose of large items as described here:


Letter from the BEO:
---

Bulky Waste Collections

Dear Residents,

We'd like to remind everyone about the process for arranging bulky waste collections.

Recently, there have been a few instances where large and/or inappropriate items have been left in communal areas/car park without going through the proper collection channels.

We completely understand that disposing of larger items can be inconvenient at times, and our aim is always to make things as straightforward as possible. However, when bulky waste is not managed correctly, the estate management team is left with no choice but to arrange additional collections. Because this is an additional external service, the cost is then recharged back to the service charge – something we want to avoid. Wherever possible we do attempt to recharge offenders directly but identifying this behaviour accurately can be very difficult.

To help prevent this, please ensure that all bulky waste collections are arranged through the appropriate channels, details of which can be found on our website Bulky item collection - City of London. By following this route, we can ensure that collections are carried out efficiently, fairly, and without unnecessary additional costs for everyone.

For the avoidance of doubt, the scheduled bulk waste collections on Monday and Thursday are free of charge. This issue relates to inappropriate waste left in communal areas or car parks not collectable under the guidelines.

Thank you for your cooperation and for helping us to keep our building clean, safe, and cost-effective.

Saturday, 12 July 2025

Proposed "art screen" for 1 Golden Lane - What is it?

 DP9 Limited, on behalf of the re-developers of 1 Golden Lane have submitted a planning application to add a requirement for an "art screen".

What is an "art screen"?   I have no idea and the application does not make this clear.   Have a look for yourself by visiting the City of London planning portal and searching for "25/00824/LBC".

I have raised an objection just to note that there is no explanation of what an "art screen" is.

Here is the letter about the application from the City.  Notice the signal to noise ratio of ~1% which is typical for such letters from the City ...

Click to read the whole leter


Tuesday, 4 June 2024

1 Golden Lane - Disingenuous Sound Measures

In their recent "Community Newsletter" for the 1 Golden Lane project, Midgard present the following table:

On the face of it these sound levels look fine, you'd think.  But look closer.  Midgard are giving measures using LAeq10 Hours in plain old dB ... this is about the best way to hide noise nuisance while coming across as all clever and technical.  But ...

LAeq (Equivalent Continuous Sound Level) is a flawed measure of sound nuisance which hides problematic peaks by averaging sound energy over long periods. The LAeq 10h measure used by Midgard averages over 10 hours, no doubt including the “Reduced impact hours” in the average.

Limitations of LAeq in more detail:

  • Focuses on average energy: LAeq simply averages the sound pressure level over a specific time period. This doesn't account for fluctuations in the sound, which can be crucial for human perception of nuisance. A constant sound at a specific LAeq might be less bothersome than the same average level with frequent peaks or variations. The 1 Golden Lane work involves relatively brief bursts of extremely loud noise.
  • Ignores frequency content: LAeq doesn't consider the frequency makeup of the sound. High-frequency sounds are generally perceived as more annoying than low-frequency sounds at the same LAeq level. For example, traffic noise with a lot of high-pitched engine sounds might be more bothersome than constant low-frequency hum from ventilation even if they have the same LAeq. The noise produced by the power tools in use on the 1 Golden Lane site is often of a high piercing frequency.
  • Doesn't capture temporal aspects: LAeq doesn't consider how the sound changes over time. Sounds with sudden loud bursts or those that occur at night can be more disruptive than sounds with the same LAeq that are spread out evenly. Some of the noisiest work on the 1 Golden Lane site seems to be saved for the very start and very end of the permitted work times.
Alternative Measures that Midgard could use if they really wanted to be helpful:
  • Lmax: This metric measures the maximum sound pressure level during a specific period. It's a good way to identify potential for sudden loud noises that might be startling or disruptive.
  • Leq,n: This metric represents the equivalent continuous sound level for specific time intervals within the measurement period (e.g., Leq,1h for hourly levels). It provides a more detailed picture of how sound levels fluctuate over time.
  • Frequency weighting: Weighting scales like A-weighting (dBA) and C-weighting (dBC) prioritize frequencies that humans perceive more readily. This helps provide a better understanding of how annoying a sound might be.

Saturday, 1 June 2024

1 Golden Lane construction - noise

 In the "1 GOLDEN LANE EC1Y 0RR - Community Newsletter – May 2024" the contractors give the times they will be working during the rest of the project:

Click to read the whole newsletter

On the basis of their behaviour so far the contractor intends to make as much noise as they like during the hours they have given, except for a break from the noisiest work between 10 to noon and 14:00 to 16:00.  The City thinks this is fine.

Montcalm hotel redevelopment ... getting bigger

It seems that the Montcalm is to be enhanced.  It will be getting taller, of course.  The dark finished growth above the brickwork is the new floor (or floors):

Click to expand

More details here:  https://montcalm-at-the-brewery.co.uk/

And, of course there will be a "consultation":

Good afternoon all,

I hope you are well.

I am contacting you on behalf Montcalm Group regarding proposals for renewed investment in The Montcalm at the Brewery, 52 Chiswell Street.

Many thanks for taking the time to meet with the project team last month.

I am pleased to notify you that following several meetings with key stakeholders, our public consultation has now launched. As part of our commitment to early community engagement, we will be holding a drop-in public exhibition to share out plans.

This will take place at:
Date: Thursday 6th June
Time: 3pm- 7pm
Location: Samuel Room, Montcalm at the Brewery, 52 Chiswell Street, EC1Y 4SA

We very much hope to see you there.

For further information, please visit our consultation website, https://montcalm-at-the-brewery.co.uk/

In the meantime, if you would like to meet with the team or have any questions or comments, please do not hesitate to get in touch.

Kind regards,

Isobel