Showing posts with label decoration. Show all posts
Showing posts with label decoration. Show all posts

Sunday, 10 March 2019

Landlord’s Approval for Home Improvements.

From the BEO:
___

Landlord’s Approval for Home Improvements.
Since the new process of Landlord’s Approval came into effect last year we’ve had many applications that have been incomplete or have missing documents. Please note the following:
  1. Please do not submit your application until your sale has completed.
  2. Part of our “Permission to Proceed” process is that we need to see your contractor’s Public Liability Insurance documentation (minimum £5 million) and Waste Carrier Licence.
  3. Please ensure you submit with all the relevant documentation. This has included applications with no plans, no Waste Carrier Licence and no signed Declaration of Compliance.
  4. Page 7 of the Home Improvement Pack is a checklist of the information we need to process your application. Piecemeal applications slow the process down for everyone.
  5. If you have any queries about the process and have read the Home Improvements Pack booklet, please do contact your House officer for further advice and assistance.
  6. Any incomplete applications will be returned to the leaseholder for their action.
Please download the check list here and click here to see the complete Home Improvement Pack.

Sunday, 19 March 2017

Vandalism in Ben Jonson House

It seems that some people have taken to vandalising bits of Ben Jonson House. Letters and symbols have been scored into lift doors.  It will cost £158.66 inclusive of VAT (at the latest estimate). per lift to fix the damage, so it's no small matter. If you have information about this please let Sheila Delaney, our house officer, know (Sheila.Delaney@cityoflondon.gov.uk).

Click to see more of one of the vandalised doors

Tuesday, 2 August 2016

Home Improvements

The recent update letter from the BEO included links to the newly updated information for those wishing to carry out home improvements.

The City has a home improvements page on their website:

Click to visit the home improvements page
... and there is a new version of the Home Improvements Pack which covers everything from asbestos to Garchey removal.  Gripping, and important, stuff:

Click to read the whole pack

Sunday, 5 July 2015

More Shadows

It's not just the barrel vaulted ceilings with shadows, it seems.  Here are some shadows in a 3rd floor flat:

Click for larger image
The resident who sent this image thinks the shadows are caused by strips of the ceiling being cooler than the rest of the ceiling, and the cool strips attracting moisture which in turn attracts dust, which in turn leaves the darker areas.

I'll ask the BEO if this shadow problem is common across the block and estate, and if so what they think is the cause and what they recommend to deal with it.

Thursday, 2 July 2015

Ghosts or Shadows on your barrel ceiling?

Residents have seen ghosting or shadow marks appear on the ceilings of rooms with barrel vaulted roofs.  I have been sent photos (below) of one example.  I understand this is not an isolated case, and that others have reported seeing this too.

There are a number of theories about the cause and what to do about it, but if you see this in your flat contact the BEO for advice.

If you have had this problem in your flat and have fixed it, please let me know how you did it so I can put the information here on the blog for others.

Click the image for a larger view

Wednesday, 18 March 2015

Long term redecoration agreement

From time to time the City sends out proposals to enter long term agreements which may have an impact upon the service charge.  This time they are proposing to enter a long term agreement with a decorations firm to look after the internal and external redecorations.  Read the details here.

The key paragraph.  I've asked the City to send proper PDFs, but they won't.

Thursday, 5 February 2015

Barbican Estate Redecoration Works

From the City:

Dear House Group Chairs and representatives,

We write to advise you of the department's intention to commence a procurement process for a redecoration contractor.

The intention is to procure a longer term contract for redecoration works for a number of blocks, This is a change from the current approach of procuring individual short-term contracts for one or two blocks. The reason for the change is that we are confident this approach will yield cost savings for residents.

The same quality requirements will be used to specify the work, as used in previous redecoration projects.

Some concerns have been raised regarding flexibility within a longer term contract, for example, if works needed to be brought forward or pushed back, subject to condition surveys. We have sought contractual advice on this point, and we are able to use a contract type which allows for such flexibility, for example, a contract which guarantees a minimum level of work and sets out, but does not guarantee, the maximum amount of work.

The programme is attached for your reference. The works have been planned using the cycle of 7 years for external redecorations and 10 years for internal redecorations, subject to condition surveys. (N.B. not all blocks are part of this programme, as such, for some Chairs and Representatives this is for information.)

In December 2014, the Barbican Residential Committee approved the project, subject to further consultation with House Groups.

If you or your members have any comments, I would be grateful if they could be returned by Friday 6th February.

Full statutory Section 20 lessee consultation will then be carried out prior to any procurement commencing.

Please do let me know if you have any questions or require any further information.

Kind regards,
Amy

Amy Carter
Asset Programme Manager
City of London

Sunday, 25 January 2015

Do the survey ... win some champagne?


Just in case you missed it, question 17 of the redecoration survey reads:

17. To be entered into the draw to win a bottle of champagne, donated by K & M Decorators, please leave your name and address below.

If you do just one survey this year, perhaps this is the one:  https://www.surveymonkey.com/s/32BJ8TQ

And, for question 4, the one thing the committee would like to see happen to improve things is to do all the planning and contractor selection in the year before redecoration is to happen so work can start in the spring, and be sure to finish before the cold weather of autumn.

Thursday, 22 January 2015

External Redecorations Survey

From the BEO:

Dear residents.

Ben Jonson House, external redecorations

We refer to the above works which were recently completed. We would like to thank residents for their patience and co-operation whilst these works were carried out. In order that we may continually improve our services, we value feedback from residents.

We invite you to please use the link below to make your comments and suggestions:
https://www.surveymonkey.com/s/32BJ8TQ

Please can we have your comments by Friday 6 February.

With regards
Barbican Estate Office
Link to website http://www.cityoflondon.gov.uk/services/housing-and-council-tax/barbican-estate/Pages/default.aspx





Sunday, 18 January 2015

External Redecoration Complete

The external redecorations work is now complete. The whole project took ~24 weeks / ~6 months.

Many residents predicted that the works would run into the winter months and that this would mean a worse job. They have been proved right on the timing. The next few years will tell us about the impact on quality. For the next external redecorations we must ask the BEO to get the bidding and planning out of the way the year before the redecoration is due to happen so work can start in April or May.

Here is the confirmation that all work is complete from Steve Murray:

With the re-decs, yes we are all done now and Sheila will be putting the sat surveys out very soon.

We do hope for a good response as the general feeling is the project has gone very well and all are happy, this as well as the planned maintenance / roof repairs and re[placing DG windows of the access equipment to utilise this and to save costs so with all the different works to co-ordinate things have gone well indeed. Of course residents have been a big help in achieving this with making and keeping appoints etc….

Regards,

Steve Steven Murray
Property Services Team Manager
Housing Property ServicesDepartment of Community & Children's ServicesCity of London
CorporationSteven.murray@cityoflondon.gov.uk
T: 0207 029 3915
M: 07786 855 580

Sunday, 7 December 2014

External Redecorations: Week 19

At the end of week 19 (w/c 1st Dec) work has reached the eastern end of the building.

There have been some reports of the paint work suffering because of the recent damp and cold weather.  If you know of areas which may need to be revisited please let Sheila or Steve Murray know by email to the estate office.

There will be one last inspection run by Sheila (see invitation here).  This will held on Tuesday 16th Dec at 14:00.  Meet on the podium by staircase 64.  If you have any comments/suggestions/concerns then please do go along.

End in sight

Sunday, 30 November 2014

External Redecorations: Week 18

At the end of week 18 (w/c 24th Nov) of the external redecoration the scaffolding around Golden Lane is starting to come down.   With the scaffolding and netting in place north facing rooms were much darker.  It's good to have the light back.

Main decoration work is now underway on the eastern part of the block.

Until this week I've had overwhelmingly positive feedback.  This week though, for the more eastern work, I've been told that the finishes are not so good and that new paint is blistering already with people suspecting the poorer weather of late being a factor.

Do let Sheila Delaney (our house officer) and Steve Murray (redecoration project lead for the BEO) know if you have any problems with the work.  Do let them know as soon as you can.

Monday, 24 November 2014

External Redecorations: Week 17

At the end of week 17 (w/c 17th Nov) of the external redecoration.

The work on the eastern part of Ben Jonson House is well under way.   The bridge across Golden lane is in place and being used by the decorators.

Please do add a comment to this post or send a message to the house group committee if you have anything you'd like to sat about the redecoration.

Here 'til Christmas?

Monday, 17 November 2014

External Redecorations: Week 16

At the end of week 16 (w/c 10th Nov) of the external redecoration project we now have the bridge over Golden Lane, so work on the northern facing parts of  Ben Jonson House over the road can start.

I understand this bridge will be in place until mid December.

Breton House in almost done.  They only needed scaffolding for the decoration of the barrel roofs.  Everything else could be done by just walking around the balconies.

Back at Ben Jonson House, scaffolding is now moving along the eastern most part of the house.

Will it be all over for Christmas?

Sunday, 9 November 2014

External Redecorations: Week 15

We're at the end of week 15 (w/c 3rd Nov) of the external redecoration project.

Here is an update from Steve Murray.  Note in particular that the scaffolding around Golden Lane will be in place until (assuming the plans don't change) 14th Dec.  Another month.  Here is Steve's note :
We now have confirmation on the road closure to erect the scaffold over Golden Lane, this will be done next weekend 15th / 16th Nov with it being dismantled 13th / 14th Dec, the main works will be at street level to build up to the height of the podium as we are not going to allow works outside residents windows at this time, the rest can be erected as normal during the week. 
Sheila is also going to put a notice up in the lifts etc…for this 
Breton House is now nigh on complete with works going to programme on the third stage of Ben J. 
A letter has gone out already but you may want to remind the residents that we have a walk around planned for Ben Jonson @2pm and Breton @3pm next Wednesday where they can bring any issues up or of course pass on any feedback. 
Thanks, Steve
Steven.murray@cityoflondon.gov.uk
0207 029 3915
07786 855 580

Sunday, 2 November 2014

External Redecorations: Week 14 (with squirrels!)

We're at the end of week 14 (w/c 27th Oct) of the external redecoration project.

We still have the scaffolding up around Golden Lane, and it will have to stay there for some time. Golden Lane must be closed while a scaffolding bridge is built, the flats above Golden Lane must then be painted and, the bridge taken down again.  A resident heard that the scaffolding would be around in this location until Christmas(!)  I've asked Mr. Murray what the plan is for this bit of the project.

... and, as a result of the scaffolding, there was a break-in this morning! ... by a squirrel. The affected resident tackled and ejected the intruder without too much difficulty, but beware!  Don't leave windows open wide enough for greys while the opening is unattended.

I also heard a report that one of the storage room doors was painted while closed, and was stuck shut when a resident visited.  I've let Steve know about this too.

Saturday, 25 October 2014

External Redecorations: Week 13

We're at the end of week 13 (w/c 20th Oct) of the external redecoration project. Here is an update from Steven Murray.   Please do let Steve or Sheila know if you are aware of anything which can be improved upon with the work, and please do attend the walk around Steve mentions if you can:

<here is> a rundown on the last couple of weeks on the re-decs for you to share on your blog.

The second stage of Ben Jonson is now 80% complete, Sheila is going to send out a letter to the residents of this section to invite them for a walk around with me and the project team to go through any issues before I sign of as complete, this will be for Wednesday 12th November at 2pm. Scaffold on the north elevation of BenJ for the final stage will start being erected from this coming Monday to complete up to the far eastern end of the block and painters will be starting on common areas and balconies from the middle of next week. A newsletter from the contractor for the residents of the final stage will also be out with info of contact details and programme.

Breton House is now also 80% complete and mostly just the eyebrow windows to do from scaffolding, as above we will have a resident walk around, this will follow at 3pm.

We of course have the little section of windows that are over Golden Lane that need to bridge the road, we are chasing for the date when we can close the road over a weekend so this can be erected.

The project has gone very well so far so fingers crossed it stays this way now we are approaching the home straight – of course this is a team effort and the residents have been fantastic with accommodating the painters and helping with making their appoints for leading edges on doors etc….so pass on my thanks for this so far.

Just let me know if there's any questions

Regards, Steve

Steven Murray
Property Services Team Manager
Housing Property Services
Department of Community & Children's Services
City of London Corporation
Steven.murray@cityoflondon.gov.uk
0207 029 3915
07786 855 580

Sunday, 19 October 2014

External Redecorations: Week 12

During week 12 (w/c 13th Oct) the scaffolding has moved eastwards, but there is a gap. Golden Lane will need to be closed while the scaffolding bridge is built to close the gap shown in this photo.

Do remember to call to make an appointment (call Charlie Demsen on 0796 185 9201) to have your woodwork varnished, otherwise the work will be done while the windows are closed and the finish will not be so good.



Gap to be filled

Sunday, 5 October 2014

External Redecorations: Week 11

Week 11 (w/c Mon October 6th).

The redecoration action has reached the middle of the house. The fire doors are looking very red, the soffits (the ceilings over the balconies) are being painted white and the windows and doors facing south are being varnished. Ours looks very nice now.

It's best to be at home when the door and window frames are being varnished. The finish is much better if the work can happen with the doors and windows open and the varnish allowed to dry that way. Call Charlie Demsen on 0796 185 9201 to arrange a time for yours to be done.

... and here is an update from Steve Murray:
Scaffold is being erected up to the west side of Golden lane north elevation of BenJ and I expect to see painters working here from the middle of next week so residents can expect to see them from then – they will then start on the scaffold the other side of Golden Lane, I’m waiting to be up-dated on the road closure needed to bridge over Golden Lane so the middle section can be done and will let you know the date for this asap, works are also on going on the south elevation of BenJ and good progress is being made.

Breton Hse is well under way and again good progress has been made on the top 3 floors and residents can expect to see painters on the 3rd & 2nd floors from Mid to late next week.

There is a resident walk on the first stage of the project set up by Sheila for next Weds 8th at 2,30 pm where I will be available to meet anyone that would like to go over anything with me.

Sunday, 28 September 2014

External Redecorations: Week 10

Week 10 (w/c Mon Sept 29th):  Work is moving east.  I even saw a workman doing some actual decorating near staircase 63 last week.

We also have a new newsletter from K&M.  One thing to note in particular:  the work is due to run well into November when the weather will be much cooler and wetter.  Will this affect the quality of the finish as some fear?