BJH Repair Costs Breakdown

The BEO have responded to our request for a breakdown of the repair costs which we requested because they were 85% over estimate as reported here.

Note that the comparison below is between actual 2013/14 vs. 2014/15 and not between estimated vs. actual (which is what we asked for), but this breakdown does let us see where the money has been spent.

Water penetration is the largest single number by far (at £151,115).  We will now be asking why the leaking roofs are not covered by the guarantee we were given when the roof works were done.
____

Ben Jonson House repairs comparison
2013/14
2014/15
Drains- Contract/Routine Works
3,514.85
2,939.17
Fire Equipment - Contract
612.64
         
Carpentry
8,389.37
10,647.93
Concrete Repairs
169.38
Decorating
849.04
266.58
Frames - Doors and Windows
3,787.12
4,581.83
Miscellaneous Works
311.43
18.86
Metalwork
4,150.48
6,908.85
Lightning Conductors
392.00
Lock Repairs and Replacement
783.90
846.70
Expansion Joints (Other Than Water Penetration)
628.00
Glazing
6,816.13
26,395.47
Balconies (Other Than Water Penetration)
876.82
1,430.54
Drains Other
5,243.00
13,315.12
Water Penetration
58,095.08
151,115.46
Sub Total
93,991.24
219,094.51
Pest Control
906.78
986.37
General maintenance (estate wide)
7,740.35
4,782.09
Electrical repairs common parts
3,798.34
3,725.24
Electrical repairs exterior
6,919.97
6,037.02
Water supply works
4,029.65
731.07
Safety/security
14,464.81
3,576.82
Sub total
37,859.90
19,838.61
131,851.14
238,933.12