Sunday 17 December 2017

BMH Work Schedule w/c Mon 18th Dec

BMH demolition continues, and still no news on the high court action.
___

Monday 18th to Friday 22nd December
  • Core drilling and breaking holes to floors and walls to secure cladding with straps.
  • Scaffold striking to reduce the scaffold as the demolition progresses through the building.
  • High level demolition to main tower.
  • Processing of demolition arisings.
  • Removal of demolition arising via Brackley Street.
  • Deliveries and collections as per Construction Traffic Management Plan.

The consented standard working hours are:
Monday to Friday 08.00 to 18.00
Saturday 09.00 to 14.00
No Sunday work

Consented quiet times are
Monday to Friday 10.00 to 12.00
Monday to Friday 14.00 to 16.00

Site Manager, Gary Telford on +44 797 615 0854.