Saturday, 19 May 2018

Concrete Repairs - dates

The long planned concrete repair works (that residents will be paying for) are finally getting under way.  In a notice from the BEO (see below) there is a link to a diagram claiming to show when work is currently expected to happen, but it's truly the world worst Gantt chart PDF (see original here) because the row headers are only present on the first page (and we're on the third page).

After hacking the document around it seems that Ben Jonson House will be tackled in project week numbers 23-29, so between 6th November and 17th December.

Click to enlarge this snip from the GANTT chart

Here is the notice from the BEO:
___
Please be aware that from June 4, Structural Renovations Ltd will be starting the Concrete Repairs Programme across the Estate. These repairs follow the detailed condition survey that was carried out in 2014/15.

Before the project begins, could residents please note the following:
Working hours are Monday to Friday, 8-5pm in common parts and 9-5pm on the balconies. Noisy works, when required, 10-4pm.
  • No operatives will be on your balcony before 9am
  • The work will commence from the roof level downwards and may involve abseiling where required. Operatives will require balconies for access. Please remove any valuable/moveable objects, plants etc. from the balcony for safe keeping. The contractor cannot be held liable for any breakages that may occur to items on your balcony.
A programme of works for the whole estate is available to residents here or on the website here. The programme is subject to change due to external forces, such as extreme weather.

Should you have any queries or concerns please contact the allocated Project Manager, Neil Clutterbuck by email neil.clutterbuck@cityoflondon.gov.uk