Wednesday, 23 April 2014

Schedule for replacing the seats


The seats and planters on the highwalks which appeared early last year, surprising us all, are to be replaced with facsimilies of the ones which were there in the first place.

I asked Steve Presland when this will happen. Here is the schedule:
  • Receive final quotes from manufacturers – 16th April 
  • Appoint manufacturer – 17th April
  • Manufacture period (4-6 weeks) – 21st April to 30th May
  • Relocation of existing seating – 09th to 13th June
  • Installation period of new seating – 16th to 20th June.

No comments :